Arkansas Construction Lien Playbook

Every notice, every deadline, in the order you have to meet them. Built to work from, on the job, not just at the desk.

2026 EditionCurrent thru 2026 1st Ex. Sess.
Set your lens: who are you on this job?
Your lien rises or falls on the Pre-Work Notice (Step 1). Hand it to the owner before you mobilize. Miss it and you lose the lien, though a suit on the contract for the balance generally survives.
No pre-work notice is required of you, but you still ride the 10-day to 120-day filing track (Steps 3 and 4). Watch substantial completion; that starts your 120-day clock.
On commercial work your 75-Day Notice (Step 2) is the one that saves you. On residential work, confirm the general contractor sent the pre-work notice; if not, you may send it before your own work begins.
01Res.

Pre-Work Notice

BEFORE WORK BEGINS

On residential projects (four units or fewer), give the owner, the owner’s authorized agent, or the owner’s registered agent the exact statutory warning (Attachment A) before you commence work (§§ 18-44-106 and -107 define “owner” and “contractor”). Deliver it personally, send it by certified mail (no signature required), or incorporate it into the signed contract. Given by the contractor before work begins, it covers every later claimant, including subcontractors, laborers, and suppliers. Two exceptions and one limit on that coverage are set out under “Who must give notice” in Part II.

§ 18-44-115Miss it: no lienExceptions: bond or direct sale
02Com.

75-Day Notice

≤ 75 DAYS AFTER LAST WORK

On commercial real estate (any nonresidential property, or residential property with five or more units), serve the owner and the contractor within 75 days of your last labor or materials provided. This notice (commonly called the “75-Day Notice”) must state that you are currently entitled to payment and have not been paid. It describes the labor, service, or materials and the amount due and unpaid, gives your name and address and the name of the person who contracted to purchase them, identifies the job site, and includes the Attachment B language. Subcontractors, service providers, material suppliers, and laborers all owe this notice (see Part II).

§ 18-44-115Must be served on owner + contractor
03All

10-Day Notice

≥ 10 DAYS BEFORE FILING

Before you file a lien, give the owner at least ten days’ notice, stating that you hold a claim against the improvement, the amount due, and from whom it is due. Keep verified proof of delivery. This notice is required on every project, residential and commercial alike.

§ 18-44-114
04File

File the Lien

≤ 120 DAYS

File a verified lien with the circuit clerk of the county where the property sits, within 120 days of your last labor or materials (for contractors, substantial completion). Include a correct legal description of the property, an accounting of the amount due after all credits, and proof of every required notice. The recording fee is $15 for the first page and $5 for each additional page.

§ 18-44-117A street address voids the lien
05Sue

Foreclose

≤ 15 MONTHS OF FILING

Enforce the lien by filing suit and a lis pendens within fifteen months of recording. Miss the fifteen-month deadline and the lien is void by operation of law. Winning alone does not earn you a fee: to recover one, first serve notice of the filed lien on the owner by one of the service methods the 75-day notice allows, then go twenty days unpaid, and only then sue. If instead the owner prevails, the owner is allowed a reasonable fee against you.

§§ 18-44-119, -128Miss it: lien void
Residential contractor · pre-work punch listStep 01
Commercial sub / supplier · 75-day punch listStep 02
All projects · notice-to-file punch listSteps 03–05

Recent legislative changes

Lenders can now prime a mechanics’ lien.

Act 479 of 2025 rewrote lien priority. It narrows how far a mechanics’ lien relates back against a construction lender’s mortgage and creates a new lender “affidavit of non-commencement” safe harbor. Record that affidavit before work begins and the lender’s mortgage takes priority over later liens. § 18-44-110 · eff. Aug. 5, 2025