Dobson & VinesAR Construction Lien Guide · 2026 ed.

Know your lien deadlines before they pass.

Arkansas construction liens run on a fixed clock, and the courts enforce it strictly. Enter your dates below to see when each notice and filing is due, then work the steps in order.

Deadline calculator

Interactive · web only
75-Day Notice due
–
commercial subs/suppliers · § 115
Send 10-day notice by
–
to still file on day 120 · § 114
Lien filing deadline
–
120 days · § 117
Foreclosure deadline
enter record date
15 months from recording · § 119
Serve fee notice by
enter record date
outer limit · 20 days before the § 119 wall · § 128

The fee notice is not a lien deadline. Serving notice of the filed lien and then waiting twenty days is what earns the claimant a fee under § 18-44-128; the date above is the last day that wait still fits inside the fifteen-month foreclosure window, not a target. Serve it early.

Calculated dates are planning estimates only, computed by calendar day from the dates you enter. They are not legal advice, and weekend, holiday, and fact-specific rules can move them. In the printed PDF this becomes the static deadline table below.

Filter the steps to your role
Your lien rises or falls on the Pre-Work Notice (Step 1). Hand it to the owner before you mobilize. Miss it and you lose the lien, though a suit on the contract for the balance generally survives.
No pre-work notice is required of you, but you still ride the 10-day to 120-day filing track (Steps 3 and 4). Watch substantial completion; that starts your 120-day clock.
On commercial work your 75-Day Notice (Step 2) is the one that saves you. On residential work, confirm the general contractor sent the pre-work notice; if not, you may send it before your own work begins.
1Pre-Work NoticeBefore work begins
On residential projects (four units or fewer), give the owner, the owner’s authorized agent, or the owner’s registered agent the exact statutory warning (Attachment A) before you commence work (§§ 18-44-106 and -107 define “owner” and “contractor”). Deliver it personally, send it by certified mail (no signature required), or incorporate it into the signed contract. Given by the contractor before work begins, it covers every later claimant, including subcontractors, laborers, and suppliers. Two exceptions and one limit on that coverage are set out under “Who must give notice” in Part II. A residential contractor who does not give this notice loses its right to lien, and commits a violation punishable by a fine of up to $1,000. Subcontractors, laborers, and suppliers lose the lien only if the owner never received the notice from anyone; one copy, from any claimant, protects them all. The current rule bars the lien only, not a suit for the unpaid contract balance, and Arkansas appellate courts have applied that softened rule retroactively, so a claim on the contract generally survives. § 18-44-115
275-Day NoticeWithin 75 days
On commercial real estate (any nonresidential property, or residential property with five or more units), serve the owner and the contractor within 75 days of your last labor or materials provided. This notice (commonly called the “75-Day Notice”) must state that you are currently entitled to payment and have not been paid. It describes the labor, service, or materials and the amount due and unpaid, gives your name and address and the name of the person who contracted to purchase them, identifies the job site, and includes the Attachment B language. Subcontractors, service providers, material suppliers, and laborers all owe this notice (see Part II). § 18-44-115
310-Day Notice10 days before filing
Before you file a lien, give the owner at least ten days’ notice, stating that you hold a claim against the improvement, the amount due, and from whom it is due. Keep verified proof of delivery. This notice is required on every project, residential and commercial alike. § 18-44-114
4File the LienWithin 120 days
File a verified lien with the circuit clerk of the county where the property sits, within 120 days of your last labor or materials (for contractors, substantial completion). Include a correct legal description of the property, an accounting of the amount due after all credits, and proof of every required notice. The recording fee is $15 for the first page and $5 for each additional page. The lien must contain a correct legal description of the property. A street address is not a correct description, and Arkansas appellate courts have held that a description so broad it cannot identify the improved area fails for the same reason. § 18-44-117
5ForecloseWithin 15 months
Enforce the lien by filing suit and a lis pendens within fifteen months of recording. Miss the fifteen-month deadline and the lien is void by operation of law. Winning alone does not earn you a fee: to recover one, first serve notice of the filed lien on the owner by one of the service methods the 75-day notice allows, then go twenty days unpaid, and only then sue. If instead the owner prevails, the owner is allowed a reasonable fee against you. The fifteen-month deadline is hard: if the claimant does not file suit and a lis pendens by then, the lien is void by operation of law. The fee is separate and can be lost without losing the lien: the claimant’s fee depends on notice of the filed lien and the twenty-day wait, so informal notice, or suing before the twenty days run, forfeits it. Those twenty days must also fit inside the fifteen months. §§ 18-44-119, -128

Deadline reference

The fixed statutory intervals. This is the table that prints in the PDF.

StepWhoDeadlineStatute
Pre-Work NoticeResidential GCBefore work begins§ 18-44-115
75-Day NoticeCommercial sub/supplierWithin 75 days§ 18-44-115
10-Day NoticeAnyone filing10 days before filing§ 18-44-114
File the LienAll claimantsWithin 120 days§ 18-44-117
ForecloseAll claimantsWithin 15 months§§ 18-44-119, -128
Notice of filed lien (fees only)Claimant seeking a fee20 days before suit§ 18-44-128

The first five are lien deadlines: miss one and the lien fails. The last is a fee condition only, and the owner has a mirror-image right to a fee if the owner prevails.

Recent legislative changes

Lenders can now prime a mechanics’ lien.

Act 479 of 2025 rewrote lien priority. It narrows how far a mechanics’ lien relates back against a construction lender’s mortgage and creates a new lender “affidavit of non-commencement” safe harbor. Record that affidavit before work begins and the lender’s mortgage takes priority over later liens. § 18-44-110 · eff. Aug. 5, 2025